Every aging condominium eventually faces a concrete restoration project, and how well that work is planned often decides whether it protects the association’s finances or drains them. We recently hosted a CEU course featuring Tara Lyn Stone from Stone Building Solutions, who guided licensed community association managers through the full lifecycle of concrete repair, from the first signs of deterioration to the final closeout report.

This vital webinar examined how community association managers can lead restoration projects with clarity and control, covering reserve funding changes, hidden sources of damage, the main repair types, the sealed bid process, and the documentation that keeps a project accountable from start to finish.

Disclaimer: This video is for educational purposes only. You will not receive credits for watching the recording. Credits were issued only to those that attended the course.

If you enjoyed this video, check out our YouTube channel and subscribe to view all of our educational videos relating to community association management in Florida.

Key Takeaways

  • Reserve Funding Rules Are Shifting: New Fannie Mae and Freddie Mac underwriting standards mean condos funding reserves at baseline levels risk losing conventional loan eligibility, which can lower unit values across an entire building.
  • Hidden Damage Drives Real Costs: Poorly sloped balconies, blocked drains, and tile laid over concrete trap water against the slab, corroding rebar and creating deterioration that surface-level inspections alone cannot reveal.
  • Destructive Testing Protects the Budget: Investigating conditions before bidding lets engineers anticipate the true scope, so boards work from one realistic number instead of facing escalating mid-project change orders and surprises.
  • Process and Documentation Matter: A disciplined timeline, weekly meetings, detailed specifications, and organized closeout records keep restoration projects on schedule, on budget, and fully backed by valid manufacturer warranties.

Why Does Concrete Restoration Feel So Urgent Now?

Financial rules that once stayed in the background have moved to the center of every restoration conversation. In March 2026, Fannie Mae and Freddie Mac issued new underwriting rules for conventional condo loans, replacing a limited partial review with a far deeper project review. If an association uses a reserve study to prove adequacy, it must now fund to the highest recommended amount, and baseline funding options are no longer accepted for these loans.

The stakes reach well beyond paperwork. When a building cannot support conventional financing, buyers struggle to close, units linger on the market, and values slide for every owner rather than only those trying to sell. For Florida condominium communities, this makes proactive reserve planning and a well-run structural integrity reserve study more important than ever.

Hidden Damage That Drives Up Costs

What you cannot see in a Florida condominium is usually what costs the most, because most concrete problems begin quietly and out of sight.

Almost every concrete problem in Florida traces back to water and where it ends up. Balconies that are not sloped correctly let water sit until it works into the slab, and drains that were installed then covered by screen enclosures, tile, or furniture leave that water nowhere to escape. Over time it migrates through the structure, reaches the rebar, and accelerates corrosion.

Tile laid directly over concrete is a frequent culprit. When the grout cracks and the waterproofing beneath it fails, moisture gets trapped between the tile and the slab, sitting against the concrete and deteriorating the rebar below. Corroded railing fasteners and cracks along the slab edge are other early warnings, especially once edge cracks begin meeting in the middle and running the full perimeter. Many of these conditions show up in three-story, garden-style condo associations where wind-driven rain has nowhere to drain.

Mapping the Restoration Timeline

A concrete restoration project follows a predictable sequence, and each stage takes roughly a month, so a board hoping to start in the dry season often needs to begin planning well in advance.

A project moves only as fast as the decisions behind it. Setting a standing weekly meeting the moment the contract is signed, not when construction begins, keeps the board engaged and prevents the process from stalling for months at a single decision point. Even fifteen minutes a week builds the cadence that carries a project through bidding, permitting, and construction.

Destructive testing often feels like an unnecessary expense, but it exists to answer one question: how bad is the damage really? Opening up representative areas before bidding lets the engineering team anticipate the full scope, so the number the board hears at the start is close to the number they pay at the end. Coming in under budget is always better than returning to owners for more money after an assessment or loan is already in place.

“We are not doing a good job as owners, reps, and engineers if we tell you a project’s going to be a million dollars, and it ends up at three million.” - Tara Lyn Stone, Stone Building Solutions

With the scope defined, engineers walk the property with chain drags and sounding tools, listening for hollow or delaminated concrete and marking findings on simple color-coded maps. Getting onto at least sixty percent of balconies provides a reliable sample, and quantifying the linear feet of slab edge, the square footage of overhead work, and the number of chair rails turns guesswork into measurable numbers a contractor can price accurately.

Despite how dramatic a condominium restoration site can look, the underlying repair categories are limited and predictable. Concrete is placed in sections and repaired in sections, and knowing the categories helps managers read a bid and confirm the work being billed.

A full-depth repair goes completely through the slab, to the point where you can see from the top surface down to the bottom. A partial-depth repair, the most common type, involves chipping away concrete until the rebar is exposed, then continuing an inch or two beyond so the bonding agent can fully coat the steel. A clean, hard-angled cut matters here; rounded edges and poor bonding are why patches pop loose within a couple of years.

Slab edge repairs address the visible edge of the balcony, while overhead work covers anything repaired from below and usually costs more because of the working position. Chair rail spots, the small orange and brown marks that appear on a surface, show where the support holding the rebar sat too close to the surface when the concrete was poured. Each category is measured separately during inspection so quantities are clear before work begins.

Railings are a life-safety system, and their anchorage is the only thing holding them in place. When fasteners corrode, water funnels down into the railing and collects at the base plate, which sits sealed against the concrete. Trapped there, it corrodes the railing from the inside out and works into the fasteners and concrete below, often causing far more damage than a visual check would suggest.

Sealant is one of the smallest line items and one of the most important. The wrong product, or a hardware-store substitute that cannot handle Florida heat, fails quickly and lets water back into the assembly. Walkway coatings deserve the same respect; they are not cosmetic paint but a barrier that keeps standing water from reaching the slab on the surfaces that take the most foot traffic.

How a Detailed RFP Protects the Budget

A strong scope is what turns three separate bids into a fair comparison. When specifications spell out repair depths, approved materials, waterproofing requirements, and verified quantities, boards can compare bids on equal footing instead of guessing what each contractor included. Vague proposals invite change orders and disputes once the work is already underway.

This is also where contractor qualifications and legal review protect the association. Confirming licensing, insurance, and relevant experience before signing prevents the costly situations that arise when a contractor is hired on price alone. A well-built concrete restoration RFP does more than gather numbers; it defines the entire project before a single repair begins.

“It’s much better to come in under budget than have to come back for more.” - Tara Lyn Stone, Stone Building Solutions

Oversight, Closeout, and Records

Active oversight keeps a project honest. Marking and measuring repairs by unit lets everyone agree on what was actually done, since linear-foot pricing adds up quickly on a large building. Payment applications should be tied to a walkthrough and a punch list that reaches one hundred percent completion before any check is released, with the board committing to pay promptly once that standard is met.

Documentation is what makes a warranty real. Keeping every payment application, daily report, photograph, and permit organized throughout the project means the contract, manufacturer warranty, and permit can be combined into one record and stored where a future manager can find it. Too many associations discover, years later, that no one collected the paperwork a valid warranty depends on.

Planning Around the Paint Cycle

The most sustainable way to manage concrete is to tie it to a building’s paint cycle. Exterior painting should happen every seven to ten years, sooner for coastal buildings, and once a building passes twenty-five years, concrete restoration belongs in every paint and waterproofing cycle. Layering the two prevents the deferred deterioration that turns routine upkeep into a multi-million-dollar emergency.

“Once buildings get over 20, 25 years old, you should be considering concrete restoration with every single paint cycle that you do.” - Tara Lyn Stone, Stone Building Solutions

Leading a Successful Restoration Project

Concrete restoration rewards managers who plan early, insist on detail, and keep the board informed at every step. Coordinating this work alongside obligations such as Florida’s milestone inspection requirements helps associations protect both their structures and their finances. When restoration is treated as a disciplined, well-documented process rather than a one-time emergency, it becomes a predictable investment in the building's future, safeguarding property values and keeping the community financially healthy for years to come.

Frequently Asked Questions

Do the new Fannie Mae and Freddie Mac rules apply to buildings under three stories?

Yes. The updated conventional loan requirements apply to condominium associations regardless of building height, so even one and two-story condos are affected.

How long should a partial-depth repair last before it shows problems?

A properly executed repair should hold for many years. Patches that pop within two or three years usually failed because of a rounded cut, weak bonding, or removal that did not extend far enough past the rebar.

Does funding to the highest recommended amount mean fully funding our reserves?

No. The highest recommended amount refers to the level your reserve provider recommends, usually a threshold model that keeps a reasonable cushion, not funding one hundred percent of every component. Full funding is generally considered unrealistic, which is why a threshold approach is the standard recommendation.

Keep informed with Florida Association News (FAN), your source for legal updates, educational resources, and practical community association guidance.

Ashley Dietz is the VP of Marketing at Campbell Property Management and has led the company’s educational and marketing initiatives since 2013. A Florida Atlantic University graduate with a bachelor’s degree in communications, Ashley specializes in community association education, digital outreach, and industry engagement for Florida HOAs and condominiums.

avatar

Ashley Dietz, VP Marketing

Ashley Dietz Gray has been handling the marketing at Campbell Property Management since 2013. She is a native Floridian who shines at building relationships and getting things done with a positive attitude. Ashley graduated Summa Cum Laude from Florida Atlantic University with her bachelor’s in communications in 2010. Prior to joining Campbell, Ashley handled the marketing for a large credit union based in South Florida. She has always believed “knowledge is power” and has made it Campbell’s mission to offer free education in the form of in-person events and webinars as well as through their blog, Florida Association News (FAN), to Board Members and Property Managers of condos and HOAs throughout Florida. She has worked hard to spread the word about FAN, which currently has over 35,000 subscribers. Ashley is a dedicated “boymom” to her two young sons, Logan and Fisher. She and her husband, Corey, reside with their boys in Boca Raton.

RELATED ARTICLES